H.B. 1261: What It Would Mean for Electric Transmission and Distribution Projects

On November 20, 2026, Representative-elect Chris Spencer (R-Hughes Springs) prefiled H.B. 1261, the “Texas Private Property and Public Necessity Protection Act.” The bill would add a new Subchapter E to Chapter 2206 of the Government Code and amend Chapter 21 of the Property Code. It applies to every condemnor, public or private, and expressly names public utilities, power facilities, transmission lines, and “utilities, transmission” among the projects it covers. It controls over conflicting condemnation grants elsewhere in the codes, including Utilities Code Chapters 181 and 186.
If passed, the bill would take effect January 1, 2028, but only if voters approve a companion constitutional amendment at the November 2, 2027 election. If the amendment fails, the bill has no effect.
Biggest Practical Impacts for Electric Utilities
A PUC certificate of convenience and necessity would no longer be enough. A CCN, PUC route approval, franchise, or other certificate “does not dispense with” the new requirements, which apply notwithstanding the condemnation grant to electric corporations in Utilities Code Section 181.004 and the railroad-crossing provisions of Chapter 186. In court, neither the PUC’s approval nor the utility’s own determination receives any deference, so routing and need issues already decided at the PUC could be relitigated parcel by parcel. The PUC could issue guidance but couldn’t create exceptions.
Investor-owned utilities would lose any new grant of authority, and their existing authority would be in question. Private for-profit companies, which include investor-owned transmission and distribution utilities, couldn’t hold or exercise a new state-law delegation of eminent domain after the effective date. The bill also says only the state or an elected governing body may authorize a taking, with written parcel-specific findings. That sentence isn’t expressly limited to new delegations, so it could be read to require a vote of an elected body for each utility project. Existing authority is otherwise left to the bill’s transition provisions and constitutional law.
Lines serving private customers would be vulnerable. A taking is prohibited if its primary purpose is private commerce, increased private profit, or a public-private venture principally supplying private economic return. Generation tie lines, lines built mainly to serve a single large customer such as a data center or industrial facility, and lines tied to private generation could be challenged on this ground.
Forecast-driven and pass-through lines would face a hard necessity test. “Public necessity” requires an immediate, critical need that directly benefits the general public, “including the local population where a taking occurs.” Speculative growth projections alone don’t qualify. Backbone and extra-high-voltage lines justified by load forecasts, or lines crossing counties they don’t serve, would be hard to defend.
County elections would be required before suit. A project that would condemn more than 100 acres or land from more than 10 owners needs a majority vote in every affected county. At a typical 150-foot right-of-way, about 5.5 miles of line exceeds 100 acres, and nearly any transmission line crosses more than 10 owners. Protected land needs a two-thirds vote. The procedures are described below.
There would be no possession before a final necessity ruling. Either side may take an interlocutory appeal, and the appeal stays all activity on the parcel. A deposit, bond, emergency declaration, or commissioners’ award doesn’t change that. In-service dates set by ERCOT or the PUC would not shorten this process, and a self-created deadline isn’t proof of necessity.
Compensation would be at least 200% of fair market value. Severance damages, relocation, restoration, business interruption, and the landowner’s appraisal and legal fees come on top of that floor. Because these costs flow into transmission rates, the bill would raise costs to retail customers.
Fiber and tower leases on the right-of-way would be shared with former owners. The bill excludes “general utility tariffs” that can’t be attributed to a parcel, so transmission cost-of-service revenue is likely outside the revenue-sharing requirement. But site-specific commercial revenue is not excluded. Leases of fiber capacity on the line, telecommunications attachments on structures, and other third-party uses of condemned right-of-way would have to be accounted for and paid annually to former owners.
How the Bill Would Treat Different Electric Condemnors
Investor-owned utilities and transmission companies. As private for-profit companies, they couldn’t receive any new delegation of eminent domain. Their existing authority under Section 181.004 would remain only to the extent the transition provisions and constitutional law protect it, and every new petition would still have to satisfy the necessity, panel, hearing, election, and compensation requirements.
Electric cooperatives. Cooperatives condemn under Utilities Code Section 161.125, which the bill doesn’t list by name. They are still covered by its general “notwithstanding” language. Their member-elected boards aren’t “elected political-subdivision governing bodies,” so it is unclear whether a cooperative board could authorize a taking or would be treated as an “unelected governing board.”
Municipally owned utilities. A city council is an elected body and could authorize a taking, but only after considering each project and adopting written parcel-specific findings. A staff filing or general ordinance that doesn’t identify parcels can’t substitute (new Sec. 2206.053(h)). City utilities would still need county elections for projects that meet the thresholds, including in counties outside the city.
River authorities and other appointed-board utilities. Bodies with appointed boards appear to be “unelected governing boards,” which couldn’t hold a new delegation of eminent domain.
Pre-Filing Requirements
Before filing a petition or threatening involuntary possession, the utility must prove, tract by tract and interest by interest, by clear and convincing evidence, a present public necessity, that the parcel is indispensable, that no feasible alternative exists, and that the taking is the least intrusive means.
Feasible alternatives expressly include conservation, demand reduction, technology, design changes, other routes or sites, existing property, and a lesser estate, even if not the utility’s cheapest or preferred option. Landowners will argue that reconductoring, upgrading existing lines, paralleling existing right-of-way, grid-enhancing technologies, storage, or non-wires alternatives make a new corridor unnecessary.
A three-member independent panel appointed by the district court reviews the necessity record and issues a recommendation within 90 days of a complete submission. This review would be in addition to the PUC’s CCN proceeding, and the panel need not agree with the PUC.
At least 90 days before filing, the utility must deliver the full project record, including alternatives, demand evidence, impact assessments, the panel report, and parcel-specific findings, to owners, counties, and cities.
Confidentiality and trade-secret designations can’t shield necessity information. Load-forecast data, large-load customer information, and critical-infrastructure details may be reviewed under a protective order, but can’t be used to prove necessity if withheld from the owner and the judge.
Local Elections Before a Petition Can Be Filed
When an election is required
A majority vote is required in each county where a taking would occur if the project proposes, in aggregate, to condemn more than 100 acres or property of more than 10 separate owners. Easements count. Cotenants count as one owner, and a person owning several parcels counts once.
All reasonably foreseeable phases, connected parcels, related routes, substations, access roads, and affiliates are added together, and a project may not be split to stay under the thresholds. A line and its associated substation and switching station would likely be treated as one covered project.
A two-thirds vote is required in each county containing “protected land,” regardless of project size. Protected land includes USDA prime farmland, active timberland, watershed or recharge land, bottomland hardwood forest, ranches held by the same family for 25 years, and homesteads. Much of rural Texas would qualify, so most long lines would face the two-thirds threshold somewhere along the route. The utility must also prove by clear and convincing evidence that a route avoiding protected land is infeasible.
How the election works
The utility files a complete, verified application with each county’s commissioners court and deposits the election costs, and the court must then order the election. The ballot must state the project, maximum acreage, general route, necessity claimed, beneficiaries, and the interest to be taken.
No election may be held until after the panel report and the county hearing. Under the Election Code, measure elections are generally held on the May or November uniform election dates.
Approval in one county can’t substitute for another. A single “no” county blocks condemnation there, which for a linear project could mean reopening the route at the PUC. Failure to hold an election is treated as a denial, and a material change to the route or acreage requires a new vote.
Easements and Post-Acquisition Terms
An easement must be narrowly described by area, duration, permitted uses, access, future expansion, restoration duty, and termination. A corridor award isn’t blanket authority for unrelated future facilities. Utilities that rely on broad easement language for added circuits, voltage upgrades, distribution underbuild, or communications facilities would need to specify those rights up front.
Former owners may repurchase if the property isn’t put to the stated use within 10 years. Planning, permitting, and financing don’t count as use. Right-of-way acquired for a future second circuit or a later phase could be subject to repurchase if not used within that time. The price is the original compensation, adjusted for CPI.
Enforcement, Emergencies, and Transition
The Attorney General and affected owners may sue for injunctive or declaratory relief, and owners who win recover their attorney, expert, appraisal, and court costs. The Comptroller would maintain a public registry of covered projects and, within 180 days, flag private and unelected condemnors and propose conforming repeals to the Legislature.
The only emergency exception is a narrow, temporary court order for access when there is a documented imminent threat to human life. It doesn’t authorize a permanent taking. Reliability needs, storm hardening, and load growth would not qualify on their own.
The bill applies to petitions filed, and acquisitions begun under an express threat of condemnation, on or after January 1, 2028. A CCN or route approved before then doesn’t protect parcels for which no petition has been filed. Utilities with approved routes should plan to file remaining petitions before the effective date.
Projects subject to federal law are exempt only as far as federal law requires, and the utility must identify the specific federal authority in a verified public filing. Because most ERCOT transmission isn’t subject to federal siting authority, this exception would rarely apply to Texas lines.
Status
H.B. 1261 was prefiled on November 20, 2026, and hasn’t been referred to committee. The 90th Legislature convenes January 12, 2027. We’ll monitor the bill and its companion constitutional amendment and will send updates as they move. A separate update addresses the bill’s effect on pipeline projects.